Overview
QM performed Demolition and Engineering services to remove the existing concrete bridge (circa 1928) adjacent to the Metrolinx rail corridor. The bridge spanned approximately 17 metres by 24 metres wide and was about 1.2 metres thick. A full road closure between Lakeshore Road and Front Street on Yonge Street was implemented and scheduled for six consecutive weekends to complete the work. QM Environmental was tasked with mobilizing every Friday and de-mobilizing every Sunday to ensure the road was opened for vehicular and pedestrian traffic the following Monday.
QM Environmental Services:
From October to December 2022, QM Environmental provided the following services to the client:
- Full Engineered Demolition Procedure
- Pre and Post-Demolition Surveys to verify and confirm all existing conditions to remain were not impacted
- Vibration monitoring
- Installation of an 18” sand bed on the road to protect and cushion falling debris
- Blast mats were held in place via crane to protect the adjacent construction site from falling debris during the removals of the 1.8m thick abutment wall
- Water truck utilized for dust suppression and clean-up of road
- Road cleaner/sweeper utilized for road clean up before opening the road for vehicular/pedestrian traffic
- All concrete and rebar were hauled to an approved recycling facility
Project Info
Client:
EllisDon
Project Timeline:
October – December 2022
Location:
Yonge Street, Toronto, Ontario