Construction and Installation of a Sediment Debris Trap Structure
QM LP was selected by the District of North Vancouver to complete a sediment basin construction project at Gallant Creek.
Project Scope
The work involved: tree removals, clearing and grubbing, construction of earth berms, construction of a gravel access road, creek channel forming and armouring, and installation of a steel straining structure to act as a debris trap to minimize flooding and debris infiltration into Deep Cove.
QM was also responsible for maintaining erosion and sediment control measures and water quality based on permit and environmental monitor requirements.
QM Services
QM Environmental’s team performed the following services, among others:
Results
Project Info
Client:
District of North Vancouver
Location:
North Vancouver, BC
Services Used:
Environmental Remediation, Soil Remediation
Timeframe:
April – October 2018
Project Value:
Undisclosed